top of page
Automated drilling machine

Automated drilling machine

The aim of this project was to learn what it would take to build a small section of an automated production line.

Early sketch

Early sketch

Construction v1.0

Construction v1.0

Pre-Assembly

Pre-Assembly

Drill column components before assembly.

Drill Column Assy

Drill Column Assy

Switching Hub Schematic

Switching Hub Schematic

This drawing determined the wire routes and hardware components to be included in the switching hub board.

Control Module Switching Hub

Control Module Switching Hub

This assembly acts as a hub, routing power and signal between the various electronic components of the machine.

Control Boards Module

Control Boards Module

This subassembly demonstrates standardization of hardware components such as connectors, modularity, and improved system documentation.

Control Module Cabinet

Control Module Cabinet

Components of control module preceding assembly.

Control Module Cabinet

Control Module Cabinet

Control Module Cabinet

Control Module Cabinet

Program testing

Program testing

Much work is left to do in organizing the mess of wires and control boards. Some mechanical kinks to work out as well.

bottom of page